News & Updates Construction Updates

We’re proud to report that the construction of Willow is well underway. To keep up to date on its progress, register your interest to have updates sent straight to your inbox. You can also see our community come to life via our live site camera.

In progress:

Stage 3

Estimated: August 2021

View Details

98%

Planning100%


Planning100%


Civil Construction100%


Site Establishment100%


Bulk Earthworks100%


Drainage Works100%


Sewer Works100%


Water & Gas Reticulation100%


Subgrade Placement Works100%


Electrical & NBN100%


Footpaths/Asphalt/Linemarking100%


Practical Completion100%


Registration Progress25%


Statement of Compliance99%


Lodge Plan of Subdivision0%


Titles0%


Settlement0%


Close Details

Stage 4

Estimated: August 2021

View Details

98%

Planning100%


Planning100%


Civil Construction100%


Site Establishment100%


Bulk Earthworks100%


Drainage Works100%


Sewer Works100%


Water & Gas Reticulation100%


Subgrade Placement Works100%


Electrical & NBN100%


Footpaths/Asphalt/Linemarking100%


Practical Completion100%


Registration Progress25%


Statement of Compliance99%


Lodge Plan of Subdivision0%


Titles0%


Settlement0%


Close Details

Stage 5

Estimated: Q4 2021

View Details

55%

Planning100%


Planning100%


Civil Construction64%


Site Establishment100%


Bulk Earthworks100%


Drainage Works100%


Sewer Works100%


Water & Gas Reticulation100%


Subgrade Placement Works80%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Settlement0%


Close Details

Stage 6

Estimated: Q4 2021

View Details

52%

Planning100%


Planning100%


Civil Construction57%


Site Establishment100%


Bulk Earthworks100%


Drainage Works100%


Sewer Works50%


Water & Gas Reticulation100%


Subgrade Placement Works60%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Settlement0%


Close Details

Stage 7

Estimated: Q2 2022

View Details

34%

Planning80%


Planning80%


Civil Construction13%


Site Establishment100%


Bulk Earthworks20%


Drainage Works0%


Sewer Works0%


Water & Gas Reticulation0%


Subgrade Placement Works0%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Settlement0%


Close Details

Stage 8

Estimated: Q2 2022

View Details

17%

Planning50%


Planning50%


Civil Construction0%


Site Establishment0%


Bulk Earthworks0%


Drainage Works0%


Sewer Works0%


Water & Gas Reticulation0%


Subgrade Placement Works0%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Settlement0%


Close Details

Completed:

Stage 1

Complete: June 2021

Stage 2

Complete: June 2021

Want to hear more?

Register to learn more about Willow Gisborne.

Register Your Interest
I would like to receive:
(Choose both or one)

By continuing you are agreeing to the Privacy Policy and Disclaimer.

Marketing opt-in