Sales & Construction Update

The Willow team has made significant progress on site this month, with more exciting project milestones on the horizon in the coming weeks.

Works in Stage 16 have progressed smoothly throughout April, with electrical installation nearing completion and footpath and driveway concreting works ongoing! Furthermore, topsoiling works are set to commence in the coming weeks.

Over in Stage 16B, bulk earthworks and sewer installation works are now complete! Drainage works have now commenced on site, with water and gas installation works to follow.

Excitingly, Practical Completion of the civil works in the Wetlands is expected imminently, with landscaping works to follow shortly after!

With now less than one week to go, there is still time to save $20,000 on Titled Lots* until April 30th! Get in quick, limited Titled Lots are available and this opportunity won’t stick around. Speak to our friendly team in the Sales Office to find out more on how you can save big at Willow.

Contact Our Team Today
View Construction Updates Page
View House & Land Pacakages

* Terms and Conditions apply.

Want to hear more?

Register to learn more about Willow Gisborne.

Register Your Interest
I would like to receive:
(Choose both or one)

By continuing you are agreeing to the Privacy Policy and Disclaimer.

Marketing opt-in
Close
Register